ReviewBuilding
Review Date04/26/2021
StatusApproved
Comments
Sheet A-001-Architectural Plan: Door schedule and hardware information is not found on the drawings. Please provide the schedule and door hardware schedule on the drawings to verify compliance with the door and hardware requirements of the Virginia Construction Code.
Code Reference: VCC 2015 Sec 1010
******************************************************************************************************************04-26-2021: Incomplete Response. I’m sorry I do not understand the door schedule as presented. Door and hardware schedule require that the doors be labeled on the floor plans so that the doors can be identified. There are 6 doors shown on the floor plan (excluding freezer doors), but only 5 shown on the door schedule. Schedule is required to show compliance with door egress and accessibility requirements. Also, door with glass, for example interior passage door, requires safety glazing. Field verify existing door hardware types and include on door schedule. It appears that the bathroom door is to receive egress (exit) hardware? Please provide the minimum door hardware function description, for example, storeroom, passage, closet function, exit, etc.
  



  
 